Project Timetable
Access Alliance’s upgrade of Great Northern Highway commenced in 2008 and is anticipated to conclude in February 2010. The upgrade has been undertaken as a series of work packages, enabling increased attention to detail and improved work outcomes. Some work packages have now been completed, with others still under construction.
In the tables below, the timetabled upgrade works are listed according to their status – Current, Upcoming or Completed. Under each category, works are listed geographically, beginning at works closest to Perth.
Current Works
To find out more about works being undertaken this week, visit our
Weekly Update
page.
Location
Description of Works
Estimated completion date
Brockman Bridge to Bindoon: Flat Rocks Road Intersection
Works area – approx 1.7km in length
-
Road realignment
- Upgrade intersection
May 2010
Upcoming Works
Location
Description of Works
Estimated completion date
Completion of revegetation works
Approx 50ha
Planting of 50,000 seedlings in disturbed and resumed areas
Winter planting season - July 2010
Completed Works
Location
Description of Works
Completion Date
Chittering Roadhouse
Approx 2.1km in length
·
Construction of turning pockets for entry to the roadhouse
·
Construction of two new driveways for the roadhouse
·
Construction of acceleration/ passing lane to north of the roadhouse
·
Improved road run-off drainage
·
Relocated Telstra and Western Power services
New signage and line markings
May 2008
Walebing to Bindi Bindi
Approx 16km in length
·
Widened road seal
·
Lowered crests and realignment of bends to improve geometry
·
Improved road drainage
Upgraded signage
March 2009
Bindoon (Longbridge Gully) to New Norcia
Works area - approx 31km in length
·
Road widening
·
Realignment & construction of passing lanes at Longbridge Gully, Hay Flat Road and Seven Mile Well
·
Surface Correction
·
Upgrade road drainage
Upgrade signage
December 2009
Great Northern Highway, Brand Highway and Muchea East Road Intersection
Works area - approx 1.4km in length
·
Intersection widening and Brand Hwy realignment
·
Construction of left and right turning pockets
·
Installation of traffic lights and sensor technology
·
Upgrade of street lighting
·
Relocation of Telstra and Western Power services
Installation of new signage and road markings
April 2010
Bindoon South: Hart Drive to Tea Tree Road
Works area - approx 4km in length
·
Road widening and realignment
·
Construction of turning pockets into Hart Drive, Chittering Road and Cobble Road
·
Improved access to the Holy Trinity Church
·
Improvement of road drainage
Installation of new signage and road markings
April 2010
New Norcia to Waddington
Works area – approx9.3km in length
·
Road widening and realignment
·
Construction of northbound passing lane
·
Capaproa Brook bridge upgrade, including improving approaches to the bridge
·
Installation of 2 stock underpasses
Improvement to road drainage
March 2010